Acceptance procedure of fire hose

2022-07-27 17:56

Acceptance procedure of fire hose

The absence, damage and corruption of the fire hose will make the indoor fire hydrant system lose its firefighting effect, so the inspection of the fire hose should not be ignored. In the process of fire control inspection, we should focus on the product model, conformity certificate documents, function measurement and other aspects of the fire hose.


municipal hose


1. Specify the model requirements of the fire hose in the design document. The material and length of the fire hose are generally required in the design document.

 

2. Check the material and model of the fire hose on site. See if the material and length are consistent with the design.

 

3. Check the certificate of conformity of the fire hose. Check whether the type inspection report, certificate, fire product information mark and other materials are complete and effective, and whether the content is consistent with the fire hose on site.


4. Measure the length of the hose and check whether the coupling is firm.


5. Water ejection test. After checking the above contents, the fire hose should be sampled for the actual water connection test. The test point should be selected the most favorable point of the hydrant system, and the pumping water injection test should be carried out. The test results should meet that there is no water leakage in coupling and lining, no slippage or water leakage in the joint binding place, and no obvious water leakage in the close connection with the hydrant.


Water Hose


Get the latest price? We'll respond as soon as possible(within 12 hours)
  • This field is required
  • This field is required
  • Required and valid email address
  • This field is required
  • This field is required